Project Overview
Challenges
Solutions
Results
Renovation to build-out new ambulatory space with over twenty exam rooms and three consult rooms serving hundreds of patients daily. Work included the addition of two new rooftop mechanical units, exam rooms, nursing stations, restrooms, and a waiting area. To complete the project on-schedule, the Wise team leveraged a Lean approach, using a continuous workflow, starting from the east side of the building and working towards the west.
Significant schedule delays due to zoning and variances
Wise’s lean construction approach enabled the build-out to be completed in 10-weeks
The new facility, a community fixture, opened on-time to service hundreds of patients despite a unforeseen schedule delays.
Healthcare
Boston Medical Center
Boston
7,100 SF
Pediatrics, Occupied Renovation, General Medicine, Behavioral Health

Confidential Client

Boston University

Watts Water Technologies