Project Overview
Challenges
Solutions
Results
Transformation of the 14th floor to build-out laboratory and support spaces, including wet and dry labs, microscopy, liquid nitrogen manifolds, dewar storage, cryo freezers, and a cold room. Scanning and BIM coordination solved problems ahead of time enabling an extensive MEP conversion scope to occur seamlessly in the field.
High Ceiling Heights; Occupied Renovation; Crane Pick over Adjacent Construction Project; Compressed schedule
3D Coordination/Scanning for Existing Conditions; Coordination with Neighboring Contractor; Identification of Long Lead Items; Early Release of Critical Schedule Items
Completed on time and on budget
Healthcare
Dana-Farber Cancer Institute
Boston
e4h
15,500 SF
Office, Occupied Renovation, Laboratory, BSL

Confidential Client

Boston University

Watts Water Technologies